Here is the schedule. These times are MST (-7 UTC):

Friday, May 4th:

9:00pm -> 11:00pm: Begin tagging and disconnecting servers and other hardware, and physically loading into the truck

11:00pm -> 11:30pm: Drive time from old datacenter to new

11:30pm -> 1:30am: Racking moved hardware in new datacenter, connecting and configuring new hardware

1:30am-> 3:30am: Assigning new IPs and notifying clients of new IP assignments

Was from my VPS provider. :)

This topic is now closed to further replies.
  • Recently Browsing   0 members

    • No registered users viewing this page.
  • Posts

  • Recent Achievements

    • One Year In
      Console General earned a badge
      One Year In
    • One Year In
      Twozo Technologies earned a badge
      One Year In
    • One Month Later
      Twozo Technologies earned a badge
      One Month Later
    • Week One Done
      Twozo Technologies earned a badge
      Week One Done
    • Veteran
      branfont went up a rank
      Veteran
  • Popular Contributors

    1. 1
      +primortal
      503
    2. 2
      +Edouard
      190
    3. 3
      PsYcHoKiLLa
      126
    4. 4
      Steven P.
      88
    5. 5
      neufuse
      71
  • Tell a friend

    Love Neowin? Tell a friend!