Here is the schedule. These times are MST (-7 UTC):

Friday, May 4th:

9:00pm -> 11:00pm: Begin tagging and disconnecting servers and other hardware, and physically loading into the truck

11:00pm -> 11:30pm: Drive time from old datacenter to new

11:30pm -> 1:30am: Racking moved hardware in new datacenter, connecting and configuring new hardware

1:30am-> 3:30am: Assigning new IPs and notifying clients of new IP assignments

Was from my VPS provider. :)