Recommended Posts

And VP Pence, in his role as head of the National Space Council, is heading to LC-39B for a "visit." This just after the NSC's big Commercial Space focussed meeting.

 

Love to be a fly on the wall for that one.

  • Like 2
35 minutes ago, Unobscured Vision said:

Yeah @ all of the above. Crazy how all of that has transpired. Some couldn't be helped, most of it could. Indicative of the culture of dysfunction that is in dire need of therapy at NASA.

 

SpaceX is doing what they need to be doing. So are the Scientists and Operations people who have nothing to do with the missions that are going right now. The issues are Old Space and the culture of sheer waste that perpetuates it, along with that same culture that sabotages newcomers and otherwise operates with political interests overriding the advancement of the U.S. Space Program. To me, that's really the larger problem -- and why things are in the state they're in. NASA is a program of several different, competing mindsets right now because of it.

Not just Nasa, the whole freaking government is in dire need of therapy.  So much damn waste, there is no wonder why we are in the hole trillions of dollars.  Makes me sick.

  • Like 2
  • 1 month later...

Via PoliticoSpace (Politico's space politics newsletter)

 

https://www.politico.com/newsletters/politico-space

 

Quote

SENATE PUSH FOR NEW ORION LAUNCHER: 

 

A bipartisan group of more than 30 this week lobbied top appropriators to fund a new launcher for the second Orion Spacecraft flight test, arguing that modifying the existing launcher would result in an almost-three-year delay between the first flight test and the first crewed mission.

The letter to Sens. Richard Shelby and Jeanne Shaheen, the top Republican and Democrat on the Commerce, Justice and Science subcommittee, says that building an additional launcher will “reduce time between flights and, more importantly, it will improve safety for our astronauts....Although this new launcher will require additional funding over five years, this is a worthy investment given the benefits.” A similar letter was sent to the House Appropriations Committee last month.

 

Acting NASA Admin. Lightfoot before Congress. I suggest a few Jolts before reading the whole mind-numbing POS.

 

http://spaceref.com/news/viewsr.html?pid=51330

 

>


Exploration Mission-1 (EM-1), in FY 2020. The mission will combine the new heavy-lift SLS with an uncrewed version of the Orion spacecraft on a mission to lunar orbit. A crewed mission, EM-2, will follow in 2023. 
>
NASA will likely launch its first astronauts into deep space since the Apollo program on a less powerful version of its Space Launch System rocket than originally planned. Although it has not been officially announced, in recent weeks mission planners at the space agency have begun designing "Exploration Mission 2" to be launched on the Block 1 version of the SLS rocket, which has the capability to lift 70 tons to low Earth orbit. Acting agency administrator Robert Lightfoot confirmed during a Congressional hearing on Thursday that NASA is seriously considering launching humans to the Moon on the Block 1 SLS. "We'll change the mission profile if we fly humans and we use the Interim Cryogenic Propulsion Stage (ICPS), because we can't do what we could do if we have the Exploration Upper Stage," Lightfoot said."
>


So, until the Exploration Upper Stage arrives in a minimum of 6-7 years (!!), the current Falcon Heavy is only a few tonnes less capable and BFR 1.0 will blow SLS away with either upper stage.

  • Like 1
  • 1 month later...

And the hits just keep on coming....paraffin contamination in the SLS engine plumbing. Could have been fun when LOX hit it ?

 

Anyone bet EM-1, already looking at mid-2020, slips to 2022?

 

http://spacenews.com/contamination-found-in-sls-engine-tubing/

 

Quote


WASHINGTON  NASA is dealing with a contamination problem with tubing in part of the core stage of the first Space Launch System vehicle, an issue that could contribute to further delays for its launch.

At a May 17 meeting of the Aerospace Safety Advisory Panel (ASAP) at NASAs Kennedy Space Center, panel member Don McErlean said the committee had been briefed on a late development with the core stage, being constructed at the Michoud Assembly Facility in New Orleans.

"A routine quality assurance inspection of the core stage," he said, "discovered contamination in tubing in the engine section of the core stage, which hosts the vehicles four RS-25 main engines and associated systems. That contamination turned out to be paraffin wax, which is used to keep the tubes from crimping while being manufactured but is supposed to be cleaned out before shipment."

"The prime contractor determined the vendor was not fully cleaning the tubes and it was leaving residue in the tubes," McErlean said. "This was retained as a requirement in the prime contractors spec, but it was not properly carried out." Boeing is the prime contractor for the SLS core stage, but he did not disclose the vendor who provided the contaminated tubing.
>
A spokesperson for NASAs Marshall Space Flight Center didn't immediately respond to questions May 17 about the contamination issue and its overall schedule impact on the SLS.

Yep, I saw this yesterday. Absolutely, insanely terrible QC going on with this whole project.

 

LO2 in contact with this would have been bad. Not explosively, but corrosively. Paraffin wax is a nice, stable compound used in all sorts of things but it's not the most robust thing on four wheels. At LO2 temperatures it becomes very brittle and very hard. The LO2 being corrosive to organics would have broken small pieces of the paraffin off of wherever-it-was inside the tubing and carried it inside the engines -- and then we have another event like with the Antares explosion. Almost identical timeline of destruction, but waaaaaaaay larger.

 

All because of this.

 

They gotta be more careful, and more thorough.

What gives me a bit of a giggle is that particulate frozen paraffin would be a *really big deal* in the RS-25/SSME and most all other engines 

 

however,

 

(Air & Space is the Smithsonian's aeronautics magazine)

 

http://www.airspacemag.com/space/is-spacex-changing-the-rocket-equation-132285884/?all

Quote

 

>

Of course, SpaceX goes to great lengths to prevent such a scenario. Part of the Merlin’s qualification testing involves feeding a stainless steel nut into the fuel and oxidizer lines while the engine is running—a test that would destroy most engines but leaves the Merlin running basically unhindered.

>

 

 

  • Like 2
  • 4 months later...

 

 

Yesterday NASA officially slipped SLS-Orion's EM-1 mission from December 2019 to at least June 2020,a with rumors it'll slip into 2021.

 

Now astronomer Scott Manley, also a space vblogger, says a source he knows reports  work on the Exploration Upper Stage has been halted.

 

 

Oh boy. :no: And with news that the first EUS is nearly complete (and ready for CDR), and with the second and third EUS's reportedly in various stages of construction comes this bombshell:

 

Boeing plans changes to SLS upper stages

Article link | SpaceNews.com website

Quote

BREMEN, Germany — With NASA’s decision to continue using an interim upper stage for additional flights of the Space Launch System, Boeing is working on changes to both that stage and a more powerful upper stage.

 

In an Oct. 3 call with reporters, John Shannon, vice president and program manager for the Space Launch System at Boeing, said NASA has asked Boeing to look at changes to the Exploration Upper Stage (EUS) to improve its performance.

 

Those changes were prompted by the decision NASA made earlier this year to delay the introduction of the EUS. That stage was originally planned to enter use with the second SLS mission, Exploration Mission (EM) 2. Instead, the first flight of what’s known as the Block 1B configuration of SLS has been delayed to the fourth SLS launch, likely no earlier than 2024.

 

“That has put a slow down on the Exploration Upper Stage work,” he said. “We were rapidly approaching the critical design review.”

 

NASA has asked Boeing to spend some time to try and “optimize” the EUS with the goal of increasing the amount of additional payload it can carry. Such co-manifested payloads, such as modules for NASA’s proposed lunar Gateway, would be carried on the SLS underneath the Orion spacecraft.

 

“We’re actively working through additional design opportunities to lighten the stage and increase its performance and take even more out to the lunar area, so that the Gateway can be built and we can get human boots back on the surface of the moon,” he said.

(....)

Hmm. So they need them to do more than then they were intended to do when first designed, and they need to shed weight to maximize performance.

 

Which will all be for naught if SLS is in the kind of trouble everyone is hearing ...

Yep. While this wasn't anything that could have been foreseen, what with SpaceX's rise to fame and the revolution in technologies, the amount of money spent and the time that has passed (missed deadlines, setbacks, etc.) should have made it clear that SLS was a really ill-advised project from the get-go.

 

One of the "damned if you do, damned if you don't" scenarios. At the time it appeared necessary ... now, in hindsight, a huge Charlie-Foxtrot and nobody wins.

 

:no: 

  • Like 2

The NASA Inspector General's SLS report is in, and it's fugly...

 

https://oig.nasa.gov/docs/IG-19-001.pdf

 

Ars Technica...

 


Theres a new report on SLS rocket management, and its pretty brutal

"Boeing's poor performance is the main reason for the significant cost increases."

Boeing has been building the core stage of NASA's Space Launch System rocket for the better part of this decade, and the process has not always gone smoothly, with significant overruns and multiyear delays. A new report from NASA's inspector general makes clear just how badly the development process has gone, laying the blame mostly at the feet of Boeing.

"We found Boeing's poor performance is the main reason for the significant cost increases and schedule delays to developing the SLS core stage," the report, signed by NASA Inspector General Paul Martin, states. "Specifically, the project's cost and schedule issues stem primarily from management, technical, and infrastructure issues directly related to Boeings performance."

As of August 2018, the report says, NASA has spent a total of $11.9 billion on the SLS. Even so, the rocket's critical core stage will be delivered more than three years later than initially planned--at double the anticipated cost. Overall, there are a number of top-line findings in this report, which cast a mostly if not completely negative light on Boeing and, to a lesser extent, NASA and its most expensive spaceflight project.
>
>
>

Nothing will change due to Congress and the "pork roll".

 

I, for one, don't mind this as SpaceX and BO will be the dominate major carriers, beyond Earth orbit, for the foreseeable future and these numbskulls are walking right into it.

 

Leave them to their "pork"...it does "spoil".

  • Like 1
  • 4 weeks later...
29 minutes ago, Unobscured Vision said:

popcorn.thumb.gif.463e24808c230f0bebe30f653d27daac.gif

Yes...kind of like the last few new topics....buckle up...we're not done...and share your popcorn.

  • Like 2
  • 2 weeks later...

We knew this was coming, didn't we? 

 

Business Insider...

Quote


NASA will retire its new mega-rocket if SpaceX or Blue Origin can safely launch its own powerful rockets

NASA is building a super-heavy-lift rocket called the Space Launch System to send astronauts back to the moon.

The SLS program has seen multiple delays and cost overruns, and the rocket is not reusable.

Elon Musk's and Jeff Bezos' aerospace companies SpaceX and Blue Origin, respectively, are developing comparable yet reusable (and presumably more affordable) giant rocket ships.

If SpaceX's Big Falcon Rocket or Blue Origin's New Glenn rockets come online, one NASA executive said the agency would "eventually retire"  SLS.
>
"I think our view is that if those commercial capabilities come online, we will eventually retire the government system, and just move to a buying launch capacity on those [rockets]," Stephen Jurczyk, NASA's associate administrator, told Business Insider at The Economist Space Summit on November 1.
>

  • Like 2

Wow...that came from the associate administrator who has massive political ties to the pork brokers.

 

This would entail the pork flowing for at least 3 to 4 years. A shame that the funding was not dumped to Blue origin and SpaceX though...but NASA now buys the ride in the future..on a design done solely by commercial for commercial interests. I like this direction and so will the American taxpayer...much more value for the dollar.

 

Unless one wants this...

Z310.thumb.jpg.fcb6331cf6de4d2303b3695a628b5b2c.jpg

 

"for another billion, we can land this the other end down"

  • Like 3

Yep. We knew this has been coming for a while now ... glad someone with some authority on the matter has finally confirmed what we've been predicting for, what ... two years?

  • Like 2

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
  • Posts

    • AltSendme 0.4.1 by Razvan Serea AltSendme is a minimal, cross-platform application designed for fast, secure, and private peer-to-peer file transfers. It allows users to send files or entire directories directly between devices without relying on cloud servers, accounts, or any personal information. Everything is encrypted end-to-end using modern protocols like QUIC and TLS 1.3, ensuring both strong security and low-latency performance. Transfers are verified with BLAKE3 for data integrity, and interrupted downloads automatically resume, making the experience reliable even on unstable connections. You can transfer anything—images, videos, documents, and more. Integrity checks are performed on both ends, so your files are automatically verified for correctness during both sending and receiving. AltSendme works seamlessly across local networks or long-distance links, capable of saturating multi-gigabit connections for extremely fast delivery. With built-in NAT traversal and encrypted relay fallback, it connects devices almost anywhere. The app integrates with the Sendme CLI and will soon support mobile and web platforms. Fully free and open-source, AltSendme offers a lightweight, privacy-first alternative to traditional cloud-based services, removing size limits, upload costs, and unnecessary data exposure. AltSendme 0.4.1 changelog: Release Highlights Self-hosted relays: Run your own iroh relay so transfers don't rely on public infrastructure. Includes a full deployment template in deploy/relay/ with Docker Compose for a VPS and configuration examples for production use. Fly.io support: One-click deploy template for Fly.io, including a quick-start config (fly.dev.toml) for testing without a custom domain, plus production setup with Let's Encrypt and your own hostname. Relay settings UI: New Settings → Network panel to choose how AltSendme connects: automatic public relays, custom self-hosted URLs (with optional auth token), or disabled. Test connections, verify latency, and see live relay status in the footer. Disable relays: Turn off relay servers entirely when you only need same-network transfers (e.g. LAN). Direct connections only. No relay hop required when devices can reach each other. Android graduates from beta: Android is now part of the regular release cycle alongside desktop. APKs ship with each version (universal, arm64, and armv7). Other improvements Private relay access control via shared auth token Relay fallback notifications when a custom relay is unreachable Broadcast mode toggle in sharing settings Android release build fixes (split-per-ABI APKs, universal APK preservation) UI polish: mobile safe-area insets, dropzone layout, transfer progress animation Bug fixes for minification-related serialization issues and system tray icon loading What's Changed feat(relay): add relay status functionality and settings UI (a120cdf) feat(relay): implement custom relay server configuration and verification (51276c7) feat(relay): add configuration for private relay access and enhance observability features (48fbabf) feat(relay): enhance relay URL validation, display connection status (d4fffa0) feat(relay): add RelayChangeGuard component and enhance relay-related translations (16ba514) feat(broadcast): add toggle setting for broadcast mode in sharing UI (ca6d977) fix(relay): correct QUIC discovery port, pin image, templatize fly.dev (52a2ba5) fix: More broken serialization due to minification (67491a9) fix(android): preserve true universal APK across per-ABI builds (e9f256f) fix(ui): conditional safe-area insets padding on mobile (1182f0e) refactor(transfer): CircularRing component animation fix (944572b) chore(android): drop x86 and x86_64 release APKs, keep universal+arm64+armv7 (34ada0b) Download: AltSendme 0.4.1 | ARM64 | ~9.0 MB (Open Source) Download: AltSendme for MacOS | Android Links: AltSendme Home Page | GitHub | Screenshot Get alerted to all of our Software updates on Twitter at @NeowinSoftware
    • You are mostly right about the ephemeral nature of it. As I mention in the article, if you dont add a second device or take a backup of your account before uninstalling it, then yes you will lose access to your account. That said, in terms of actual user experience when you sync multiple devices your message history carries across and there's also a Saved Messages chat like there is on Telegram to send messages and attachments between your installs. But yh, what you point out are correct and its not trying to emulate Messenger or Telegram.
    • OK so SearXNG is a meta search engine that you can install locally or use via a public instance. It scrapes other search engines which you choose and then sorts the results. Not as complicated as multiple relays
    • The only difference here is that you think you came up with these reasons. You didn't. These age old fearmongering lies (that were NEVER true) were funded by and the anger stoked by Putin through proxies like Farage (and later in the USA, Trump) and filtered down through the skinheads, Neonazis, etc. until it reached the uninformed, ignorant, and gullible -- never realizing they were being played for fools against their own best interests. Even now, despite all of the EVIDENCE proving that Brexit was a terrible mistake for ALL citizens of the UK and that its supporters were tricked by Putin's proxies into sabotaging their own nation, you're still here defending these well-known lies as if they were ever true. Not only are they not true. They NEVER were. So, when are you going to realize that you were lied to and actually get angry at the liars and charlatans who lied to you, instead of blaming the innocent people they lied to you about?
    • Dupe of "Microsoft further improving Windows 11 Taskbar with latest builds", published <20 minutes apart
  • Recent Achievements

    • Week One Done
      flexorcist earned a badge
      Week One Done
    • One Month Later
      Woland13 earned a badge
      One Month Later
    • Week One Done
      Woland13 earned a badge
      Week One Done
    • One Year In
      bernmeister earned a badge
      One Year In
    • Week One Done
      Scoobystu earned a badge
      Week One Done
  • Popular Contributors

    1. 1
      +primortal
      495
    2. 2
      +Edouard
      225
    3. 3
      PsYcHoKiLLa
      152
    4. 4
      Steven P.
      75
    5. 5
      FloatingFatMan
      71
  • Tell a friend