This explains a few things. They subbed for Vencore on SpaceX, ULA and a lot of other projects. Presumably other subs will need to be found.

 

The OIG noted safety issues, missed completion dates, cost overruns etc.

 

http://www.orlandosentinel.com/news/space/os-nasa-oig-agents-raid-sbd-construction-contractor-20160707-story.html

 

Quote

Federal agents raid NASA construction contractor

 


Federal agents raided the Titusville office of a NASA construction contractor on Thursday, according to Orlando Sentinel news partner Fox35.

Investigators with NASA's Office of Inspector General, the agency in charge of probing crimes against NASA, removed boxes of documents and computer towers from SDB Engineering and Constructors Inc., according to Fox35.

The company located on East Parrish Road has worked on several big projects at NASA's Kennedy Space Center including upgrades to the Vehicle Assembly Building and corrosion control work at Launch Complex 41 and Launch Complex 37, used for United Launch Alliance launches.

SDB Engineering and Constructors Inc. has contracts with the U.S. Air Force, SpaceX, ULA, and previously United Space Alliance, before the Space Coast company closed in 2014, according to the SDB Inc. website.

SDB Inc. is a subcontractor for multiple companies including engineering company Vencore, audited by NASA OIG in 2016.

Vencore has a $1.9 billion overall contract with NASA's Kennedy Space Center.

The audit of Vencore was initiated because of concerns over NASA's ability to "to motivate contractor performance and improve acquisition outcomes," according to the 2016 report.

The Orlando Sentinel was unable to reach NASA OIG for comment on the ongoing investigation and calls to SDB Engineering and Constructors Inc. went unanswered.

 

  • Like 1
23 minutes ago, DocM said:

This explains a few things. They subbed for Vencore on SpaceX, ULA and a lot of other projects. Presumably other subs will need to be found.

 

The OIG noted safety issues, missed completion dates, cost overruns etc.

 

http://www.orlandosentinel.com/news/space/os-nasa-oig-agents-raid-sbd-construction-contractor-20160707-story.html

 

"to motivate contractor performance and improve acquisition outcomes"

 

That seems to be very common with regards to contractor work for our government.  It sucks.  I saw it throughout my career.  It'll cost x amount of dollars for the equipment, y amount for the installation ... and then the contractors drag their feet....come up with some excuse or find a loophole in the contract...and add additional cost/time on top of the agreement.  You're left with having to pay the additional cost/delaying operations because of them and/or the contract.

Why are cost overruns permitted?  In the real world, once you have a written quote on something, that's the price you pay, end of story.  If their costs have gone up since quoting, that's THEIR problem, not yours!

 

  • Like 3

Because that's how many govt procurements work; they get to cover increased post-contract "costs" - aka Cost Plus. How else do you explain $500 hammers and $1200 toilet seats? $36B rockets? $12B spacecraft w/only 4 seats?

 

 

3 minutes ago, DocM said:

Because that's how many govt procurements work; they get to cover increased post-contract "costs" - aka Cost Plus. How else do you explain $500 hammers and $1200 toilet seats? $36B rockets? $12B spacecraft w/only 4 seats?

 

 

Our government does not work the way it should. FFman is absolutely correct.

  • Like 2
1 hour ago, DocM said:

Because that's how many govt procurements work; they get to cover increased post-contract "costs" - aka Cost Plus. How else do you explain $500 hammers and $1200 toilet seats? $36B rockets? $12B spacecraft w/only 4 seats?

The whole corrupt lot of 'em need shoving out of the nearest airlock.  I swear, if it were left to the US gov, we'll never get to Mars...

 

4 minutes ago, FloatingFatMan said:

The whole corrupt lot of 'em need shoving out of the nearest airlock.  I swear, if it were left to the US gov, we'll never get to Mars...

 

NASA never should have been outsourced. We did get to the moon..:)

On 7/24/2016 at 11:16 AM, jjkusaf said:

"to motivate contractor performance and improve acquisition outcomes"

 

That seems to be very common with regards to contractor work for our government.  It sucks.  I saw it throughout my career.  It'll cost x amount of dollars for the equipment, y amount for the installation ... and then the contractors drag their feet....come up with some excuse or find a loophole in the contract...and add additional cost/time on top of the agreement.  You're left with having to pay the additional cost/delaying operations because of them and/or the contract.

WFA in procurement (all procurement - it's not unique to military, space, or even national-government procurement) is an ongoing problem - it gets even worse when it links to elections - and it often does, even at the subcontractor level.  (How much are contributions in LOCAL elections connected to subcontractors - even in Florida?  It has indeed become an issue in local elections merely in the DC area - consider that both corruption cases involving different former Virginia governors involve contractors or subconctractors.)

Not space related, but even after half of Detroit's major officers were sent to federal prison (the mayor got 27 years) the new mayors office is already in trouble over blight demolition contracts - kickbacks etc. and costs rising 25% a year or more. FBI investigation, probably a Grand Jury investigation etc.

 

They never learn, and at the federal level it's baked in.

  • Like 1
4 minutes ago, DocM said:

Not space related, but even after half of Detroit's major officers were sent to federal prison (the mayor got 27 years) the new mayors office is already in trouble over blight demolition contracts - kickbacks etc. and costs rising 25% a year or more. FBI investigation, probably a Grand Jury investigation etc.

 

They never learn, and at the federal level it's baked in.

Not news, DocM - it predates Watergate at the very least.  (The FBI gets involved because the national government is one of the sources for the funds via various trusts - especially the Transportation and Transit Trust Fund - which is covered by fuels taxes.)

  • Like 2

Oh yeah ... and because of DOD Regulations for procurement, development, and manufacturing for Mil, Gov, Uni and Sci Projects (and anything important marked for Civ use) all designs, components and personnel must be sourced from within the U.S. and employ U.S. Companies -- and generally if that work has anything to do with Mil, Gov, or Sci Classification then it'll charge extra "Premiums" on top of costing more since we probably don't make some of those components here anymore; so they'll need to build the facilities necessary to build the subcomponents to build the components ... (thanks to President Bush in '89 & Clinton in '93).

 

Systemic, convoluted cycles of greed and mismanagement on top of more greed and mismanagement run by barely competent people whose only goal is to occupy their time with spending money that they really aren't accountable for ... yeah, it's a [poop]show. Welcome to the great monolithic industrial machine that builds nothing on-time or on-budget anymore, because it can't. Pretty much like Microsoft, now -- a big, convoluted mess that doesn't know what it's supposed to be doing; and even when it tries it still isn't doing a very good job of it nor in a timely fashion.

26 minutes ago, Unobscured Vision said:

Oh yeah ... and because of DOD Regulations for procurement, development, and manufacturing for Mil, Gov, Uni and Sci Projects (and anything important marked for Civ use) all designs, components and personnel must be sourced from within the U.S. and employ U.S. Companies -- and generally if that work has anything to do with Mil, Gov, or Sci Classification then it'll charge extra "Premiums" on top of costing more since we probably don't make some of those components here anymore; so they'll need to build the facilities necessary to build the subcomponents to build the components ... (thanks to President Bush in '89 & Clinton in '93).

 

Systemic, convoluted cycles of greed and mismanagement on top of more greed and mismanagement run by barely competent people whose only goal is to occupy their time with spending money that they really aren't accountable for ... yeah, it's a [poop]show. Welcome to the great monolithic industrial machine that builds nothing on-time or on-budget anymore, because it can't. Pretty much like Microsoft, now -- a big, convoluted mess that doesn't know what it's supposed to be doing; and even when it tries it still isn't doing a very good job of it nor in a timely fashion.

hmmm....really?  Not doubting you ... but all of the systems we used were foreign.  For example we used a Belgium company (AGFA) for the Picture Archiving and Communications System (actually that is Air Force wide) ... and two of the radiology rooms were also AGFA with a Switzerland company being the third radiology room (SwissRay). :)  We had Toshiba for CT and Ultrasound.  In fact we couldn't upgrade to GE equipment because they hadn't been vetted through the appropriate IT security (the DIACAP monster if you're familiar) so they weren't authorized for purchase.

 

Of course...this was medical ... so it may be different than the "real" DoD and probably had some sort of waiver or whatever for the DoD regulation you mentioned. :)

 

  • Like 1
13 hours ago, jjkusaf said:

hmmm....really?  Not doubting you ... but all of the systems we used were foreign.  For example we used a Belgium company (AGFA) for the Picture Archiving and Communications System (actually that is Air Force wide) ... and two of the radiology rooms were also AGFA with a Switzerland company being the third radiology room (SwissRay). :)  We had Toshiba for CT and Ultrasound.  In fact we couldn't upgrade to GE equipment because they hadn't been vetted through the appropriate IT security (the DIACAP monster if you're familiar) so they weren't authorized for purchase.

 

Of course...this was medical ... so it may be different than the "real" DoD and probably had some sort of waiver or whatever for the DoD regulation you mentioned. :)

 

Right. That equipment fell under a certain GL Code, so it was fine.

13 hours ago, jjkusaf said:

hmmm....really?  Not doubting you ... but all of the systems we used were foreign.  For example we used a Belgium company (AGFA) for the Picture Archiving and Communications System (actually that is Air Force wide) ... and two of the radiology rooms were also AGFA with a Switzerland company being the third radiology room (SwissRay). :)  We had Toshiba for CT and Ultrasound.  In fact we couldn't upgrade to GE equipment because they hadn't been vetted through the appropriate IT security (the DIACAP monster if you're familiar) so they weren't authorized for purchase.

 

Of course...this was medical ... so it may be different than the "real" DoD and probably had some sort of waiver or whatever for the DoD regulation you mentioned. :)

 

jkusaf - there are also cases of Congressional "meddling" involving contracts for a specific agency (due to the contracting agency in question being in the district of a powerful Member of Congress - consider my own Fifth Congressional District (Maryland) and the military agencies in it (from Joint Forces Base Andrews to ONI (which is subject to DIACAP - which you just mentioned); not even DIACAP has roadblocked procurement WFA all that well)).  In short, I'm not saying that such WFA happens despite the waivers - instead, I am saying that the WFA happens due to the waivers.

This topic is now closed to further replies.
  • Recently Browsing   0 members

    • No registered users viewing this page.
  • Posts

    • Camtasia 2026.1.3 by Razvan Serea TechSmith Camtasia is the complete professional solution for high-quality screen recording, video editing and sharing. Camtasia 2026 makes editing your videos easier, and faster than ever. The new editor is packed with enhanced video processing, all-new production technology, an innovative library, and stock videos and other creative assets to help you create more polished, professional videos. No video experience needed. Anyone can create informative, engaging videos. Create professional, eye-catching videos: Add special video effects - Apply Behaviors that are perfectly designed to animate your text, images, or icons. Get a crisp, polished look without being a professional video editor. Drag-and-drop your edits - What you see is what you get. Every effect and element in your video can be dropped and edited directly in the preview window. And you can edit at resolutions up to beautiful 4K, for clear video at any size. Get exceptional performance - Camtasia takes full advantage of your computer’s processor with 64-bit performance. You’ll get fast rendering times and enhanced stability—even on your most complex projects. Camtasia 2026.1.3 changelog: Feature Updates Improved keyboard navigability in tool panels. Improved screen reader accessibility of headings in Preferences. Tool panels can now be resized using a keyboard-navigable control. Updated color of folder icon in User Library tab for better visibility. Grouped media now render a composite waveform considering all audio media within that group. Added Long Path Aware to the manifest of Editor and Recorder. Performance Improvements Improved performance for editing groups on the timeline. Improved the project loading performance when timeline has lots of trec media with cursor data. Updates for IT Administrators Updated cpp-httplib from 0.38.0 to 0.43.3. Updated expat from 2.7.4 to 2.8.0. Updated freetype from 2.13.3 to 2.14.3. Updated harfbuzz from 13.0.1 to 14.2.0. Updated libpng16 from 1.6.55 to 1.6.58. Updated pango from 1.57.0 to 1.57.1. Updated girepository from 2.86.3 to 2.88.0. Updated pcre2-posix from 10.47.0 to 12.0.2. Added new harfbuzz-gpu.dll. Updated FFmpeg from 7.1.1 to 7.1.2. Updated aom from 3.11.0 to 3.13.1. Updated dav1d from 1.5.0 to 1.5.1. Updated ogg from 1.3.5 to 1.3.6. Updated SDL2 from 2.32.4 to 2.32.10. Updated zlib from 1.3.1 to 1.3.2. Updated Nalpeiron binaries to version 4.4.69.3. Bug Fixes Fixed an issue which prevented some user submitted crash reports from being sent. Fixed a potential memory leak when decoding HEVC or VP9 video. Fixed a potential crash when trying to delete a range selection on a magnetic track. Fixed a bug with the Properties Panel showing stale properties when only a caption is selected on the timeline. Fixed an issue that could prevent the Opacity and Blur properties from being changed in the Background Removal effect. Fixed an issue where larger Camtasia online projects may fail to open in Camtasia Editor. Table of contents thumbnails are no longer created for Smart Player exports with no table of contents. Fix resetting skew revert to revert just skew and not scale as well. Fixed editing in Snagit with snagX file with Unicode characters. Fixed a bug where grouped visual media could be cropped in some cases. Fixed importing SnagX files with Unicode characters. Localization fixes. Download: Camtasia 2026.1.3 | 309.0 MB (Shareware) View: Camtasia Homepage | Tutorials | Screenshot Get alerted to all of our Software updates on Twitter at @NeowinSoftware
    • yeah it seems to be Edge only. The dialog buttons work as expected in Chrome and Firefox. The phone is using Android 16 (OneUI 8.5) and Edge version  149.0.4022.53
    • I'm not aware of this issue, but to help the other guys.  What version of Android are you using? Did you try a different browser? To see if Edge is the issue here.
    • I agree when are you going to read this (really poor BTW) article? Here is a better article so you actually know what is going on and answers questions you had in other comments --> https://arstechnica.com/gadgets/2026/05/speed-boosting-low-latency-profile-is-one-of-the-improvements-coming-to-windows-11/ It is unclear if one will be able to disable the new profile at this point but I am not seeing any reason why one would.
  • Recent Achievements

    • One Month Later
      Jamswaz earned a badge
      One Month Later
    • Week One Done
      Jamswaz earned a badge
      Week One Done
    • Rookie
      Marzoid went up a rank
      Rookie
    • Community Regular
      coch went up a rank
      Community Regular
    • One Year In
      slackerzz earned a badge
      One Year In
  • Popular Contributors

    1. 1
      +primortal
      512
    2. 2
      PsYcHoKiLLa
      188
    3. 3
      +Edouard
      157
    4. 4
      Steven P.
      83
    5. 5
      ATLien_0
      75
  • Tell a friend

    Love Neowin? Tell a friend!