With 11 more CRS Round 1 Dragon 1 flights, at least 6 CRS Round 2 Dragon 2's and at least 6 post-certification Crew Dragons (+ 2 certification flights), and god knows how many Red Dragon missions, that new Dragon Hatchery facility is gonna be hopping.

 


Jan. 3, 2017

Mission Awards Secure Commercial Crew Transportation for Coming Years

NASA took another big step to ensure reliable crew transportation to the International Space Station into the next decade. The agencys Commercial Crew Program has awarded an additional four crew rotation missions each to commercial partners, Boeing and SpaceX, to carry astronauts to and from the International Space Station.

The four additional missions will fly following NASA certification. They fall under the current Commercial Crew Transportation Capability contracts, and bring the total number of missions awarded to each provider to six.

The additional flights will allow the commercial partners to plan for all aspects of these missions while fulfilling space station transportation needs. The awards do not include payments at this time.

"Awarding these missions now will provide greater stability for the future space station crew rotation schedule, as well as reduce schedule and financial uncertainty for our providers," said Phil McAlister, director, NASAs Commercial Spaceflight Development Division. The ability to turn on missions as needed to meet the needs of the space station program is an important aspect of the Commercial Crew Program.

The two commercial spacecraft also will provide a lifeboat capability to allow the astronauts aboard the station to return safely to Earth in an emergency, if necessary.

Returning human launch capabilities to U.S. soil underscores NASAs commitment to the station and the research that the orbiting laboratory makes possible including the advancement of scientific knowledge off the Earth, for the benefit of those on the Earth and to prepare for future deep space exploration.

The Commercial Crew Program will help NASA get full operational use from the national laboratory for scientific research by increasing the number of astronauts on the space station, and allowing the crew members to dedicate more time to research.

The commercial crew vehicles will transport up to four astronauts for NASA missions, along with about 220 pounds of critical cargo to the space station.

More time dedicated for research allows NASA to better understand the challenges of long-duration human spaceflight without leaving low-Earth orbit. As NASA develops the Orion spacecraft and the Space Launch System rocket for deep space missions, including the journey to Mars, NASA is turning over low-Earth orbit crew and cargo transportation to commercial companies. This two-pronged approach is critical to achieve the agencys exploration goals.

Boeings uncrewed flight test, known as an Orbital Flight Test, is currently scheduled for June 2018 and its crewed flight test currently is planned for August 2018. SpaceXs uncrewed flight test, or Demonstration Mission 1, is currently scheduled for November 2017, followed by its first crew flight test in May 2018.  Once the flight tests are complete and NASA certifies the providers for flight, the post-certification missions to the space station can begin.

Boeing and SpaceX are developing two unique human space transportation systems. They also are upgrading necessary infrastructure, including launch pads, processing facilities, control centers and firing rooms.

Boeing is developing the CST-100 Starliner that will launch on a United Launch Alliance Atlas V rocket from Space Launch Complex 41 at Cape Canaveral Air Force Station. SpaceX is developing the Crew Dragon to launch on the companys Falcon 9 rocket from Launch Pad 39A at the agencys Kennedy Space Center. Both are located on Floridas Space Coast.

Last Updated: Jan. 3, 2017

  • Like 1

I just, in the matter of the last two weeks found out we haven't been able to get through the Van allen belts https://www.nasa.gov/content/goddard/van-allen-probes-spot-impenetrable-barrier-in-space 

 

they have been said to disrupt Computer systems and are heavily radioactive and harmful to humans. is it possible for man to get through these?

 

 

So the Van Allan belts is a barrier for the ultra-fast electrons. Not Physical items. Otherwise we wouldnt have asteroids and the Satellites that have recently visited Pluto/Jupiter.

 

The video is a bit of over exaggeration an the comments not really relevant. There is a lot of radiation that astronauts are subjected to and the goal is to shield than from this, however the radiation will not instantly kill you, similar to nuclear radiation it affected the body over time. So the goal would be to protect the astronauts as much as possible from the radiation that we know will be there. 

 

As for the computer systems, due to all of the new technologies going into Orion and newer satellite a lot of the components have never been tested with the specific type and amount of radiation they may be exposed to. So it "may" cause issues however we are unsure. The comments in the video talking abut Apollo are not really relevant due to the outdated technology that was used back then compared to now.

Yeah, a little overblown. Manned spacecraft passed through this "barrier" twice on every Apollo mission, and communication satellites and deep space & interplanetary probes do likewise.

 

Do the computers need radiation hardening or, like SpaceX does, multi-level redundancy with voting logic? Absolutely!! 3 voting processors in each computer, 3 voting computers in each control system. Or more. They believe in overkill. 

 

 

And there are sections of the belts that are a lot thinner and much less harmful than the "full monty" parts. During Apollo/Saturn, TLI and TEI trajectories were plotted in such a way where spacecraft spent as little time as possible in the VAB region(s) -- they plot through the thinnest and least active of these areas to minimize the exposure. That, in conjunction with how the CM was designed, helped a great deal.

 

image-of-Apollo-11-and-van-allen-belts.g

So there we go. The Van Allen Belts are manageable, so far as spaceflight is concerned.

  • 2 weeks later...

 

NASA: 17 Commercial Crew Things to Track in 2017 
By Steven Siceloff,
NASA's Kennedy Space Center, Florida

 

Throughout 2017, NASA and its commercial crew partners, Boeing and SpaceX, will make major steps touching every area of space system development and operations, from completing flight-worthy spacecraft and rockets to putting the finishing touches on launch pads to performing detailed countdown and flight rehearsals.

 

Here is a look at 17 things you should track for in 2017:

 

1.    Structural Test Article: Boeing begins 2017 with its CST-100 Starliner Structural Test Article at the company’s Huntington Beach, California, facility for testing that will push, pull and apply pressure to the spacecraft, qualifying that the design will be able to withstand the intense conditions encountered during spaceflights.

 

2.    Structural Qualification: SpaceX is on pace to complete structural qualification of the Crew Dragon capsule and trunk in early 2017. The company built the Crew Dragon Qualification Vehicle to prove its design will hold up to the rigors of spaceflight.

 

3.    Starliner Prototype: Boeing will wrap up assembly of its Starliner prototype, Spacecraft 1, which is slated to go through ground verification testing before flying in a pad abort test from White Sands, New Mexico. Production of two additional Starliners will ramp up in 2017 in preparation for two test flights – first without a crew to the International Space Station and then with one Boeing and one NASA astronaut on board. All three spacecraft are being manufactured in the Commercial Crew and Cargo Processing Facility at NASA's Kennedy Space Center in Florida.

 

4.    Complete Manufacturing: SpaceX also will complete manufacturing of three Crew Dragons that are currently in early phases of assembly. These spacecraft will perform Demonstration Mission 1, flight test without crew, Demonstration Mission 2, flight test with a crew aboard, and the company’s first crew rotation mission.

 

5.    Software Systems: Both companies' robust autonomous software systems will continue to be put to the test to ensure everything works exactly as planned throughout all phases of the mission.

 

6.    Starliner Thrusters: The Starliner thrusters – from small maneuvering jets to large engines that would fire in an emergency to push the spacecraft and astronauts out of danger – will be qualified and acceptance tested in the fall during the service module hot fire test.

 

7.    Draco and SuperDraco: The Draco and SuperDraco thrusters for SpaceX's Crew Dragon are on pace to complete static-fire qualification testing in the first few months of 2017. SpaceX produces both thrusters in-house. The smaller Draco thrusters maneuver the spacecraft while it's in orbit and provide small adjustments. The SuperDracos, which are 3D printed, are much larger and produce enough thrust to lift the Crew Dragon out of danger in case of an abort situation. The company expects to complete propulsion system validation testing by demonstrating capability in all phases of flight using a dedicated module by the second half of 2017.

 

8.    Parachute Tests: Boeing will start off 2017 with its parachute qualification test series in New Mexico and more advanced drop testing at NASA’s Langley Research Center in Virginia. Boeing plans to place an instrument-laden human-like test dummy inside its mockup for drop tests that will verify that the Starliner's airbags will absorb enough of the force of landing to keep astronauts safe. The landing tests will be performed using a gantry that drops the mockup onto a dirt pad.

 

9.    Parachute Development: SpaceX plans to finish development testing of its Crew Dragon parachute systems in early 2017. The Crew Dragon will use a four-parachute configuration for landing in the water. The company plans to complete qualification testing of the parachutes after the summer.

 

10.    Spacesuits: Boeing and SpaceX each designed their own spacesuits for flight, based on the systems of their respective spacecraft and NASA’s stringent requirements. Throughout 2017, both companies will subject their suits to rigorous testing in multiple circumstances that might be encountered in space. SpaceX has completed spacesuit development testing and will build the training and flight suits for its crewed demonstration flight and first crew rotation mission after astronauts are assigned to missions. The spacesuits are not designed for spacewalking, but are meant to fill the role of the orange partial-pressure suits astronauts wore during space shuttle launches and returns. They are meant to keep air flowing to the astronaut in case of depressurization and meet a host of special capabilities.

 

11.    Starliner Factory: Boeing will add to its Starliner manufacturing complex at Kennedy early in 2017 when it opens a Hazardous Processing Facility that will allow for the safe fueling of Starliner spacecraft with maneuvering system propellants before the spacecraft is taken to the launch pad for liftoff.

 

12.    Crew Access Tower: Work is nearing completion on a new structure built specifically for the needs of astronauts climbing into Boeing's Starliner as it stands atop a United Launch Alliance Atlas V rocket at Space Launch Complex 41 in Florida. In 2017, the 200-foot-tall Crew Access Tower and Crew Access Arm will see installation and testing of emergency escape systems. ULA's complex is one of the most active on the Space Coast, and construction of the systems needed to support crew launches has taken place between launches.

 

13.    Launch Complex 39A: SpaceX has overhauled the historic Launch Pad 39A at Kennedy and built new support structures for the company's line of Falcon rockets. The Crew Access Arm, currently under construction, will be connected in the spring to provide a bridge from the fixed service structure to the Crew Dragon spacecraft so astronauts can board before launch. The launch pad will be put to the test when SpaceX launches its Falcon 9 from the pad in early 2017. It will mark the first flight off of Pad 39A since the final space shuttle mission in 2011.

 

14.    Atlas V Production: United Launch Alliance will continue production of the two Atlas V rockets that will lift Starliners into orbit on flight tests with and without crews aboard. Building its rockets at a plant in Decatur, Alabama, the company will begin building the boosters for operational Starliner missions, as well.

 

15.    Falcon 9 Production: SpaceX will build up the Falcon 9 rockets that will launch Crew Dragons into orbit for the flight tests of its systems. SpaceX builds its rockets, Merlin engines and Crew Dragon spacecraft at the company's factory and headquarters in Hawthorne, California.

 

16.    Flight Test: SpaceX is slated to make its first flight test – without a crew – in November 2017. Flying to the space station using its automated guidance and navigation systems, the Crew Dragon will dock there on its own and remain for a time before detaching and parachuting back to Earth and landing in the Atlantic Ocean off the coast of Cape Canaveral. The mission will be a dress rehearsal for a later flight test that will include astronauts.

 

17.    Space Station: The advances are not limited to Earth, either. Astronauts on the International Space Station will continue modifications in 2017 tailored for new vehicles, including commercial crew spacecraft.

  • Like 2

Thanks for the update Doc. That update does sound very political trying to make it look like both are working to the same time frame. But the most telling thing is point 16, as there is not one for Starliner. But im excited to see both of them launch, hopefully they are on time or early, not delayed. 

 

Now I could go for some social commentary.

 

  • Like 2

Actually, I am impressed, that through under funding, feature creep and bureaucracy, that SpaceX has not "blown a forehead blood vessel".

 

:D 

  • Like 2

Not to mention ULA dragging the entire Program behind several years just maintain the appearance of staying relevant to it. SpaceX won this one by several miles.

 

[EDIT] In fact, SpaceX outright "skunked" them by letting it go this long ... the Aerospace equivalent of the -- drumroll -- PARTICIPATION TROPHY. *guffaw*

Edited by Unobscured Vision
  • Like 1

Boeing hurt themselves by waiting until they got a contract before cutting metal, which means paper and inventory milestones until early last year.

 

OTOH, SpaceX has been flying and refining Dragon since 2010 and started testing the SuperDraco escape/landing thrusters in 2012.

  • Like 2
  • 4 weeks later...

As much NASA not doing certifications in a timely manner as anything, 6 months instead of the contractual 2 months, and adding requirements & functions on the fly. Add those to the issues both providers have inevitably run into and here we are.

  • Like 2

Yep. As much as I'm gung-ho for safety and reliability, this is truly getting ridiculous now. NASA can't spare the people needed to do the inspections and certs?? Should take a few weeks per Provider, maximum. And being NASA, they'll have checklists. LOTS of them. If something isn't up to par, tally it up at the end and give 'em three months to address it.

 

They wouldn't like me if was NASA Administrator ... :rofl:

 

"And knock off the feature creep. We're looking at you, Managers. You've already delayed things by two years, by my count. Don't force Administration to "drain the swamp" inside your offices too, because that can be arranged. Do your ####### jobs like you've got a purpose. NO EXCUSES. Arrange for those Certification Inspections and get this #### done already."

 

Might not be PC, and certainly not NASA-PC, but threaten their cushy jobs and they'll actually move their rear ends. Instead of having "Focus Groups" and burning up coffee makers.

 

Maybe I'd even pull surprise visits on-site with the REAL people who know what's going on ... you know, the ones doing the work? I'd rather deal with them anyway. Get accurate status reports, and more importantly you find out what they need in order to finish the job in a reasonable amount of time .. and not have to listen to some Company Rep who blows glitter and unicorns and basically lies to ya the whole time other than the fact it's actually in-work.

 

Oh ... hehe ... and our guy Marty and the Wonder Workers? They'd be offered positions to help get things back on-track. I'd make Marty an offer he couldn't refuse ... :D 

  • Like 1
7 hours ago, Unobscured Vision said:

Tell 'em, Gwynne. :yes:

She is a diamond ...... one of the best hires that SpaceX made...

 

note..Elon made a twitter account for her, but she doesn't like to tweet...

 

https://twitter.com/gwynneshotwell?lang=en

 

 

  • Like 1

Considering one of those block 5's will be the un-crewed Crew Dragon mission, that's 6 before late 2018. No sweat.

 

And the whole idea of SLS flying an Orion crew early makes the above even more ridiculous. Especially given all the mission critical items on Orion which aren't near ready yet.

  • Like 2

Also heard that a few booster segments have flaws and require recasting, with additional expense. The ESA module which was due last month won't arrive till summer...but everything is fine with SLS.

 

I am beginning to think that some believe this silliness. Once FH flies...going to be tough to justify cost/lift mass.

 

edit...just found some of the references...

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This has gotten a bit out of control. Must be a "last ditch" to keep SLS going...this is really out of character.

 

At the rate NewSpace is plugging along...some questions will be answered sooner than a few want them answered.

 

:s

4 hours ago, Draggendrop said:

 

 

 

Exactly....

Not just SLS/Orion... Just how many Apollo/Saturn 5's of the same configuration did NASA launch before they started putting people in them, hmm?

 

  • Like 1

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
  • Posts

    • I notice how you dodged the questions I had about the racism shown by ignorant, gullible, cowardly people when the Poles, like your partner, were the immigrants. Ahem. I wonder how you'd feel if native born Brits suddenly treated you as "dirty crooked immigrant" for being half Trump-American? If they ordered you to leave and "go back to your corrupt country" (on the other side of the Atlantic), would you go? The truth is based on facts as supported by evidence. As requested in your previous posts, I have used the facts in your own post to show everyone the truth.
    • US citizens are paying to their government, who could use that to fund healthcare and tuition and relieve the costs of these for citizens instead of making tax breaks that overwhelmingly favor the rich. I'm not saying that tariffs are the correct solution, but what else would they be used for? What else could Trump have in mind for wanting them, if he hasn't figured out that labor costs are higher in the US?
    • I’m in need of a new chair and it sounds like the backrest cannot be locked? I also sat on a Herman miller and was devastated that it couldn’t be locked also, what is going on with chairs. I want to be able to lock the backrest into any position but not even the Herman’s do that
    • Sihoo Doro C300 Pro V2 Ergonomic Office Chair review: The Ikea of chairs by Steven Parker I've reviewed a few gaming chairs over the past three years or so and generally found them to score well in our reviews. SIHOO reached out asking if I was interested in taking a look at their flagship chair, the Doro C300 Pro V2. I never got the chance to check out its predecessor, but the V2 is described as an "Adaptive Ergonomic Chair." It became available to buy in April of this year. Let's get things rolling with a closer look at the specifications and features. Specifications Doro C300 Pro V2 Model Ergonomic Materials Mesh Back and Seat; Soft PU Coated Armrests Height adjustability 45.5 - 53 cm / 17.5" - 20.9" Seat (w+d) 52 x 43 - 47 cm / 20.5" x 16.9" - 18.5" (adjustable) Backrest 52 – 60 cm / 20.5" - 23.6" (adjustable) Lumbar support Mesh built-in (adjustable) Armrest adjustability 8D Bionic Armrests Rocking angle 105°, 120°, 135° (fixed) Neck support Mesh built-in (adjustable) Net weight 27.3 kg / 59.64 lbs Weight support 150 kg / 330 lbs Colors Black, White Warranty 5 years (upon registering) Price $499.99, $539.99 Introduction At first glance, it looks like a chair that in another life wants to be a Herman Miller; It certainly looks like my Aeron Remastered, but the Doro C300 Pro V2 has quite a few more features and costs quite a bit less. SIHOO says that it is made up of a "DynaCore" system that tracks your movement and synchronizes the headrest, backrest, lumbar support, and armrests as you shift, twist, or recline. They also say that the "SyncroFlex Backrest" molds to your spine, which kind of describes how the mesh fabric works in most ergonomic chairs, but anyway. Below are the meat and potatoes measurements for the chair. Here is the same tech sheet, but in inches. Durability I would be remiss to not talk about the various durability testing this chair underwent before coming to market, as this is claimed on the product page. First of all, the chair is BIFMA-, SGS-, and TÜV-certified. As for durability, the tests undergone were: 100,000 Castor cycles tested 120,000 Armrest cycles tested 120,000 Recline cycles tested 120,000 Gas lift cycles tested 60,000 Armrest durability cycles tested 120,000 Rotation cycles tested Nothing about weights testing, though. Now that's all disclosed, now onto my own personal findings. Assembly The Doro C300 Pro V2 came in two large boxes (1) (2), and everything was packed very well, protecting the different parts of the chair. In the box, there is a folded sheet that explains the 12 steps to assemble it; they are: Remove the bottom cover on the aluminum base; Insert the five legs into the aluminum base and use ten screws to fasten them; Insert the castors into the legs; Replace the bottom cover on the bottom of the aluminum base; Place the Class 4 Hydraulics gas cylinder into the aluminum base; Screw the bottom part of the arm rests, taking care of the orientation using two screws on each side; Use three torx screws to fasten the footrest to the bottom of the seat; Fasten the backrest to the seat using four torx bolts; Fasten the armrests to the backrest using four Torx bolts (two on each side), taking care to note the orientation; Place the chair onto the Class 4 Hydraulics gas cylinder; Insert the headrest into the top of the backrest; Use two torx screws to fasten the headrest to the backrest. There's also an online guide you can refer to. Carefully unpacking the two boxes took around 15 minutes because almost everything is wrapped in plastic and protective foam; the chair assembly itself took around an hour. I say in the above assembly steps to take note of the orientation, because it's not obvious which way around the bottom portion of the armrests go, and although there is an L and R on the bottom of the armrests, it also wasn't clear from the instructions which was actually left or right, facing the chair, or in the seated down orientation? Anyway, I ended up putting the bottom portions on the wrong sides, and after securing one of the armrests, I discovered that although it was on the correct side, the armrest base could rotate a full 360°, but not when bolted to the chair, so I had to remove it, rotate it, and then bolt it back on. Truly an Ikea experience! Also, to complicate things further, although all the parts are labeled from A to X (yes, that's 24 parts) unhelpfully, these letters do not appear on the parts themselves or the package with the bolts, screws, and washers. There's also a pair of protective gloves in the box, but I think they were made for much smaller hands than I have. Even my friend, who is 5.1, had difficulty putting them on. Once assembled, I needed to sit down. Anyway, as I said, it looks quite similar to my Herman Miller. And here is the back of it. If you look at the product page and on Amazon, it seems like a lot of thought has gone into the chair itself and what it's capable of, but there is no mention at all about the castors, and this is an area where I think the chair trips up quite quickly. I found it difficult to move the chair in any direction. I asked a friend who came to visit me earlier this week to test my findings, and she said that the wheels were "no good," so it definitely isn't just me. I am 6'2 myself and a big guy, I work from home and gained a few pounds from mostly staying in and the hell away from other people. However, the Doro C300 Pro V2 is rated for up to 150kg (330lbs), which in my case is used well within its max rating. Ergonomics The number of adjustments you can make, right up to setting it in nap mode — which I haven't fully tested yet — is what you'd expect from a premium chair. Yes, you can go up and down (max 7.5 cm adjustment), rock back and forth (with tilt adjustment), and lock the chair between three stages of 105°, 120°, 135°, which is not quite as flat as the AndaSeat I tested at 160°. Some thought has also gone into the "8D" armrests, too, which are cushioned but quite firm; you'll only know it if you press hard into the PU-covered tops, which give about half a centimeter, but it's enough to ensure your skin won't get awkwardly stuck to it in warmer (or sweatier) conditions. It almost feels like plastic and is very easy to keep clean. However, the armrest positions move far too easily, and I am not sure what that "elbow" function is. Maybe it is good for a short person with short arms, anyway, I never used it and kept it flat at all times. There are eight levels of adjustment for the armrests, they are: backwards, forwards, swing left/right, height up and down, tilt, and 360° rotation, which can be handy for desk clearance. As I said, the armrest pads shift far too easily, which could give off an ergonomic vibe, but who wants the armrest sliding when you are shifting weight? The height adjustability does lock into place when lifting and adjusting. Comfort This is ultimately what it boils down to at the end of the day, right? Quite a lot of reviews praise the comfort of this chair, and I don't disagree that the mesh seating is quite comfortable. I am used to the material from my daily Herman Miller. However, the backrest cannot be locked into place, and this is actually a feature; as you shift or recline yourself on the chair, the backrest moves with your body. It took some getting used to. The lumbar gives ample support, but I would have preferred an adjustable one built into the seat base, as this causes the backrest to move up and down at will. Again, as with my previous chair review, this chair is also rated for tall people, but nowhere in the product documentation does it say how tall. Being 6'2 myself, I'm happy to say that the backrest is tall and wide enough, and thought has been given to being able to adjust the neck rest, but as others have mentioned in their reviews, people as tall as 6.2ft is about the limit for the neckrest. Conclusion What I didn't like The footrest is rated for 15kg (33 lbs), which to me seems a bit light, and after looking online, it seems like a chair footrest for adults must be at least twice that rating. In all honesty, they are just hollow metal tubes, so it is not recommended to let a kid sit on them. I also feel like it doesn't really go out far enough for my height, so that kind of puts the dampener on me being able to use it regularly. I'll just have to continue to use my subwoofer as a footrest! I do not like the armrests being able to shift around as easily as they can, and they are a little too forward-positioned in the chair to comfortably sit close to my desk, because even in the lowest height position, they don't allow me to go under the desk like is possible with my Herman Miller. I also feel like this chair could have been delivered partially constructed, especially the armrests on the seat, and why the aluminum base wasn't already pre-constructed (without the castors) is baffling, considering it would have fit in one of the two boxes that way. The instructions also need to be clearer. On the pamphlet, there's an A to X listing (which is also used in the steps), but none of the physical parts use this lettering system! What I did like I'll be honest, I haven't used it for very long, just one week, and seating comfort is subjective after all! Any spills wiped straight off it, the stitching, and the lines look great, not a fray to be seen or stitch out of place. It looks kind of cool, too. My favorite feature of these seats is the nap mode. While you're not lying completely flat, it leans far back enough to make you easily doze off after a heavy gaming or working session. Overall, this chair offers plenty of comfort features. The MSRP does vary quite a bit depending on the region, at £549.99 in the UK, and €580 in Europe, and $599 before tax in the U.S. However, shipping is free, which is a bonus for such a heavy item. Is it worth it, though? At three years' warranty, I think it's a decent deal. Another firm out of Germany sent me a free replacement hydraulic gas spring for a chair that failed after almost four years, so it was well outside its two-year warranty. My advice is to always try, as you might have the same luck I did. If I could fault it at all, it would be the constant shifting of the armrests and backrest. Where to buy Although the footrest variant normally costs $539.99, it has been discounted to $469.99 on the official website in Black or White. In fact, the non-footrest variant is only $40 cheaper. On Amazon, it currently costs more at $499.99 links below. Sihoo Doro C300 Pro V2 for $469.99 (official website) Sihoo Doro C300 Pro V2 for $499.99 at Amazon US SIHOO provided a free sample without any review or pre-approval. Good to know This Amazon link is U.S. specific, and not available in other regions unless specified. We only use first-party seller links (at the time of article publishing); ensure that you purchase from a first-party seller link only. Check out Today's Deals on Amazon | or our recent tech deals. Become a Prime member (for Students or SNAP) via Neowin Get Prime Access - Prime for half price (for qualifying Medicaid, EBT, SNAP) Subscribe to Prime Video, Audible Plus, Music Unlimited or Kindle Unlimited via Neowin As an Amazon Associate, we earn from qualifying purchases.
  • Recent Achievements

    • Conversation Starter
      jessse3334 earned a badge
      Conversation Starter
    • Reacting Well
      JuvenileDelinquent earned a badge
      Reacting Well
    • One Month Later
      Excellence2025 earned a badge
      One Month Later
    • Week One Done
      Excellence2025 earned a badge
      Week One Done
    • Week One Done
      flexorcist earned a badge
      Week One Done
  • Popular Contributors

    1. 1
      +primortal
      506
    2. 2
      +Edouard
      207
    3. 3
      PsYcHoKiLLa
      151
    4. 4
      Steven P.
      73
    5. 5
      macoman
      62
  • Tell a friend

    Love Neowin? Tell a friend!