https://spacenews.com/missing-pin-blamed-for-boeing-pad-abort-parachute-anomaly/

 

>


The pilot parachute is designed to deploy first, and pull out the main parachute. However, Mulholland said that hardware inspections and photographs taken during "closeout" of the vehicle prior to the test showed that a pin that links the pilot and main parachutes was not inserted properly.

"It's very difficult, when you're connecting that, to verify visually that it's secured properly,” he said, in part because that portion of the parachute system is enclosed in a "protective sheath" intended to limit abrasion but which also makes it difficult to visually confirm the pin is in place. "In this particular case that pin wasn't through the loop, but it wasn’t discovered in initial visual inspections because of that protective sheath."
>

SpaceX would have been mercilessly tormented if a similar failure had occurred with Dragon 2 during it's Abort Test. We're talking internal lobbying at NASA and Washington. A hold up of no less than two years. Endless managerial and engineering red tape, recertification across-the-board, etc etc etc.

 

This is corruption culture in-work.

 

Disgusting. We all saw what happened. There's no WAY they could call that a success.

  • Like 2
  • 2 weeks later...
  • 3 weeks later...
  • 1 month later...

Oopsie...

 

https://spacenews.com/boeing-takes-410-million-charge-to-cover-potential-additional-commercial-crew-test-flight/

 

Quote

Boeing takes $410 million charge to cover potential additional commercial crew test flight

 

WASHINGTON — Boeing is taking a $410 million charge to its earnings to cover a potential additional uncrewed test flight of its CST-100 Starliner, although company officials say there’s no decision yet about whether such a flight is necessary.

The company said in its fourth quarter earnings release Jan. 29 that it was taking the charge “primarily to provision for an additional uncrewed mission for the Commercial Crew program, performance and mix.” It noted that NASA was still reviewing data from the Orbital Flight Test (OFT) mission in December that was cut short, without a docking at the International Space Station, by a timer problem.
>
>

 

  • Like 1

Ferchrissake... 😵

 

https://arstechnica.com/science/2020/02/starliner-faced-catastrophic-failure-before-software-bug-found/

 

Quote


Starliner faced catastrophic failure before software bug found

During its quarterly meeting on Thursday, NASA's Aersopace Safety Advisory Panel dropped some significant news about a critical commercial crew test flight. The panel revealed that Boeing's Starliner may have been lost during a December mission had a software error not been found and fixed while the vehicle was in orbit.

The software issue was identified during testing on the ground after Starliner's launch, said panel member Paul Hill, a former flight director and former director of mission operations at Johnson Space Center in Houston. The problem would have interfered with the service module's (SM) separation from the Starliner capsule.

"While this anomaly was corrected in flight, if it had gone uncorrected it would have led to erroneous thruster firing and uncontrolled motion during SM separation for deorbit, with the potential for catastrophic spacecraft failure," Hill said during the meeting.

>
The safety panel also recommended that NASA conduct "an even broader" assessment of Boeing's Systems Engineering and Integration processes. Only after these assessments, Hill said, should NASA determine whether the Starliner spacecraft will conduct a second, uncrewed flight test into orbit before astronauts fly on board.
>

6 hours ago, DocM said:

there is no way I'd be a passenger on it until more testing has been done successfully.

  • 3 weeks later...
  • 3 weeks later...

Crew Dragon DM-2: late May, 2020

 

https://www.nasa.gov/press-release/nasa-spacex-invite-media-to-first-crew-launch-to-station-from-america-since-2011

 

 

Quote

March 18, 2020

 

MEDIA ADVISORY M20-041

NASA, SpaceX Invite Media to First Crew Launch to Station from America Since 2011
 
Media accreditation is open for NASA’s SpaceX Demo-2 flight test, which will send two astronauts to the International Space Station as part of the agency’s Commercial Crew Program. This mission will be the return of human spaceflight launch capabilities to the United States and the first launch of American astronauts aboard an American rocket and spacecraft since the final space shuttle mission on July 8, 2011.

SpaceX’s Falcon 9 rocket will launch Crew Dragon, with NASA astronauts Bob Behnken and Doug Hurley aboard the spacecraft, from Launch Complex 39A at NASA’s Kennedy Space Center in Florida. NASA and SpaceX are currently targeting no earlier than mid-to-late May for launch.

This second demonstration mission of the Crew Dragon spacecraft is another end-to-end flight test of SpaceX’s human spaceflight system, which will include launch, docking, splashdown and recovery operations. It is the final flight test of the system before SpaceX is certified to carry out operational crew flights to and from the space station for NASA.

Media accreditations deadlines are as follows:

·      International media without U.S. citizenship must apply by 4 p.m. EDT Friday, April 17.
·      U.S. media must apply by 4 p.m. Friday, April 24.
All accreditation requests should be submitted online at:
https://media.ksc.nasa.gov

NASA is proactively monitoring the coronavirus (COVID-19) situation as it evolves. The agency will continue to follow guidance from the Centers for Disease Control and Prevention and the agency’s chief health and medical officer and communicate any updates that may impact mission planning or media access, as they become available.

For questions about accreditation, please email 

[email protected]

For other questions, contact Kennedy’s newsroom at 321-867-2468.

Reporters with special logistics requests for Kennedy, such as space for satellite trucks, trailers, tents, electrical connections or work spaces, must contact Tiffany Fairley at 

[email protected] by Friday, April 24.

NASA’s Commercial Crew Program is working with the American aerospace industry through a public-private partnership to launch astronauts on American rockets and spacecraft from American soil. The goal of the program is to provide safe, reliable, and cost-effective transportation to and from the space station, which will allow for additional research time and will increase the opportunity for discovery aboard humanity’s testbed for exploration. The space station remains the springboard to NASA's next great leap in space exploration, including future missions to the Moon and eventually to Mars.

For launch coverage and more information about the mission, visit:

https://www.nasa.gov/commercialcrew

-end-

1584901488399.thumb.jpg.2c0a141f27697fd30cae5185c0839794.jpg

NASA astronauts Doug Hurley and Bob Behnken familiarize themselves with SpaceX’s Crew Dragon, the spacecraft that will transport them to the International Space Station as part of NASA’s Commercial Crew Program. Their upcoming flight test is known as Demo-2, short for Demonstration Mission 2. The Crew Dragon will launch on SpaceX’s Falcon 9 rocket from Launch Complex 39A at NASA’s Kennedy Space Center in Florida.
Credits: NASA

 

 

  • Like 1
  • 2 weeks later...

US Crew Vehicle 1 (USCV-1) crew

 

First operational Crew Dragon mission

 

Mike Hopkins (Commander; NASA, USA) 

 

Vic Glover (Pilot; NASA, USA)

 

Soichi Noguchi (Mission Specialist 1; JAXA, Japan)

 

Shannon Walker (Mission Specialist 2; NASA, USA)

 

  • Like 2

Boeing Statement on Starliner's Next Flight

 

https://boeing.mediaroom.com/2020-04-06-Boeing-Statement-on-Starliners-Next-Flight

Quote

ARLINGTON, Va., April 6, 2020— The Boeing Company is honored to be a provider for the Commercial Crew mission.  We are committed to the safety of the men and women who design, build and ultimately will fly on the Starliner just as we have on every crewed mission to space.  We have chosen to refly our Orbital Flight Test to demonstrate the quality of the Starliner system. Flying another uncrewed flight will allow us to complete all flight test objectives and evaluate the performance of the second Starliner vehicle at no cost to the taxpayer.  We will then proceed to the tremendous responsibility and privilege of flying astronauts to the International Space Station.

 

  • Like 1
10 hours ago, Skiver said:

It's not like they have a choice - NASA was pretty ticked off after the very public OFT-1 Charlie Foxtrot.

  • Like 1
On 4/7/2020 at 8:55 PM, DocM said:

It's not like they have a choice - NASA was pretty ticked off after the very public OFT-1 Charlie Foxtrot.

I read  that they hadn't officially been told they HAD to re-test but offered Boeing the opportunity to make the right decision for themselves before throwing in their opinion.

 

Granted I think any idiot could see Nasa wouldn't have ever let them proceed to manned tests.

Well this isn't altogether unexpected ...

 

New document reveals significant fall from grace for Boeing’s space program

https://arstechnica.com/science/2020/04/a-nasa-analysis-of-boeings-lunar-cargo-delivery-plan-is-very-unflattering/

 

Ouch!

That document was written by  astronaut Ken Bowersox,

 

STS-50, STS-61, STS-73, STS-82, STS-113, Soyuz TMA-1 (down)

 

He has also excluded Boeing from bidding on future Gateway cargo awards. None. Zip. 

 

Boeing needs to deliver a 100% perfect Starliner OFT-2 flight or they'll be so screwed....

 

As for SpaceX's Dragon XL winning cargo bid,

 

Quote

SpaceX provided, by far, the highest amount of pressurized and  unpressurized cargo capability of any of the offerors, significantly exceeding the minimum cargo amounts levied by the RFP. This is true with both  SpaceX’s fast transit and slow transit concepts of operation. The SEB assigned this as a significant strength. (Significant Strength #1).  In addition, SpaceX provides for a cargo packing density that is significantly lower than the reference density of 290kg/m3 (standard for ISS cargo missions). This large usable volume will allow for cargo to be packed to optimize crew accessibility and ease of use instead of optimizing around cargo density. SpaceX’s approach allows for tremendous flexibility in manifesting the maximum amount of cargo. SpaceX’s approach to cargo design within the pressurized volume is equally impressive. The SEB assigned this as a significant strength. (Significant Strength #2).

>
SpaceX’s approach also allows for a mission extension very late in the mission with very little lead-time needed. (Strength #8). This provides flexibility in overall mission design should NASA need it. SpaceX also has an approach that exceeds requirements by having dual fault tolerance in several critical systems and single fault tolerances in others. (Strength #2). Other benefits to SpaceX’s proposal include enhanced battery capability that allows for higher performance of its spacecraft during eclipse periods when its solar arrays are not charging. (Strength #3). Finally, SpaceX offered to have its safety-critical software independently verified and validated as part of its baseline service. (Strength #7). Third party independent verification and validation (IV&V) is a beneficial feature that reduces the risk of catastrophic failures due to software. When combined, these numerous strengths will result in benefits to NASA, over and above the two significant strengths described earlier.

 

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
  • Posts

    • EU says AWS and Microsoft Azure should be treated as DMA gatekeepers by Pradeep Viswanathan Under the European Commission's Digital Markets Act (DMA), a company is presumed to be a gatekeeper if it meets certain quantitative thresholds. However, the Commission can still investigate and designate a company even if it does not meet the numeric thresholds, provided the service has a major market impact. The European Commission launched its investigations into AWS and Azure on November 18, 2025, to address unfair or anti-competitive practices in the cloud sector. Today, the European Commission has informed Amazon and Microsoft of its preliminary view that their cloud computing services, AWS and Azure, should be designated as gatekeepers under the DMA. The EC highlighted that Amazon Web Services (AWS) and Microsoft Azure are the largest and second-largest cloud computing services in the European Union. Both of these platforms act as important gateways between businesses and their customers in the EU. The EC further mentioned that AWS and Azure have reached significant turnover, built large and entrenched user bases, and benefit from high switching costs and customer lock-in. Furthermore, their operational capacity and investments appear to have outpaced those of competitors. Teresa Ribera, Executive Vice-President for Clean, Just and Competitive Transition, said the following: It is important to note that the findings are preliminary and do not decide the final outcome. Amazon and Microsoft can now review the findings and respond to the Commission. However, if the Commission confirms its preliminary findings, it will formally designate Amazon and Microsoft as gatekeepers for AWS and Azure. Once designated, Microsoft and Amazon will have six months to bring their cloud services into full compliance with the DMA’s rules and regulations.
    • will EU users be getting the extra 1yr update for free again?
    • Samsung announces Galaxy A27 5G with 120Hz AMOLED display, expanded AI features, and more by Fiza Ali Samsung has announced the Galaxy A27 5G, its latest mid-range smartphone, bringing a handful of upgrades over last year's Galaxy A26 5G. While the changes aren't dramatic, they touch several areas that people tend to notice most in day-to-day use, including the display, performance, and software support. One of the more noticeable updates is the screen. The Galaxy A27 5G comes with a 6.7-inch Super AMOLED display that now supports a 120Hz refresh rate, making scrolling and animations appear smoother. Samsung has also switched to an Infinity-O punch-hole camera design, which leaves more room for the display and gives the phone a cleaner look from the front. Under the hood, the Galaxy A27 5G is powered by Qualcomm's Snapdragon 6 Gen 3 processor. The company says the new chip brings improved responsiveness in multitasking, gaming, and media consumption. The company also highlights GPU performance improvements and faster memory technology, which should contribute to smoother graphics rendering, quicker data handling, and improved power efficiency. Furthermore, Samsung has equipped the Galaxy A27 5G with a 12-megapixel selfie camera that is capable of capturing a wider dynamic range and more accurate colours. Like many smartphones launched recently, the Galaxy A27 5G also places a strong focus on AI features. Circle to Search with Google now supports multi-object recognition, making it easier to search for different products or items at the same time. The tech giant says the feature can also support virtual outfit try-ons directly from compatible search results. Photo editing tools are getting some attention as well, with Object Eraser updated to deliver cleaner edits when removing unwanted objects or people from images. Meanwhile, the Voice Recorder app can now transcribe and translate speech simultaneously in one of the 22 supported languages, which could be useful for meetings, lectures, or interviews. Samsung is also expanding AI assistant options on the device, with support for Google Gemini and Perplexity alongside Bixby. The company says these assistants will work more closely with Galaxy apps, including Gallery, to simplify common tasks. Samsung continues to strengthen its long-term software support policy with the Galaxy A27 5G. The smartphone will receive up to six generations of Android OS and One UI updates, along with six years of security patches from its initial global launch. In terms of security, the device includes Samsung Knox and Knox Vault, which are designed to help protect sensitive information stored on the phone. On the flip side, while the company is positioning the Galaxy A27 5G as a step forward from its predecessor, not every change is necessarily an upgrade. One of the first things buyers may notice is the higher price tag. The device launches at $349, making it $50 more expensive than the Galaxy A26 5G's $299 starting price. The selfie camera has also been reduced from 13MP to 12MP, while the ultrawide camera drops from 8MP to 5MP. Samsung has further downgraded the phone's dust and water resistance rating from IP67 to IP64. The Galaxy A27 5G is also marginally thicker at 7.8mm. The Galaxy A27 5G will be available in select markets starting July 3 and will come in four colour options, including Black, Blue, Light Green, and Light Pink. The company will also offer Samsung Care+ coverage plans for customers seeking additional device protection.
    • Doogee and Ulefone regularly release phones with 10k-25k mAh batteries, but those are bricks. I don't understand how they could make it only weigh 220 grams with a battery that size.
    • Windows 10 quietly gets one more year of support and updates by Taras Buria Windows 10 reached its end of life at the end of 2025. Microsoft kicked off the Extended Security Updates program, aimed at giving regular consumers one more year of security-only updates. By doing so, Microsoft gave users more time and money to update their computers to a newer operating system or compatible hardware. Now, with the end of the Extended Security Updates program quickly approaching, Microsoft is making an important adjustment. Users discovered that the official support article for the program now lists a new end-of-support date: The Extended Security Updates program is not a new concept. It has been an official way for business consumers to continue receiving critical updates for unsupported Microsoft products for many years. However, all this time, it was a business-only, paid feature. With Windows 10, Microsoft brought ESU to regular consumers, allowing them to get security updates for Windows 10 past October 2025 essentially for free. When Windows 10 was approaching the end of support, many guessed that Microsoft might adjust its support timelines, and this is exactly what seems to be happening. Of course, Microsoft would love everyone to switch to new computers, such as its latest Surface devices, but in the days of ever-growing hardware prices, not everyone is lucky enough to have money for a new PC. Leaving hundreds of millions of customers with a Windows version that no longer receives security updates is a major risk that Microsoft is not willing to take. If you have a Windows 10 PC to enroll in the Extended Security Updates program, check out this guide to learn how to do so.
  • Recent Achievements

    • First Post
      kinowa earned a badge
      First Post
    • Rookie
      krychek57 went up a rank
      Rookie
    • Grand Master
      Jaybonaut went up a rank
      Grand Master
    • One Year In
      Philsl earned a badge
      One Year In
    • Dedicated
      Scoobystu earned a badge
      Dedicated
  • Popular Contributors

    1. 1
      +primortal
      437
    2. 2
      +Edouard
      168
    3. 3
      PsYcHoKiLLa
      133
    4. 4
      Xenon
      76
    5. 5
      Michael Scrip
      75
  • Tell a friend

    Love Neowin? Tell a friend!